Blackwell Zinc

Sampling and Analysis Plan (Sediment and Surface water)

Blackwell Industrial Authority Maintenance

BNSF Shallow Soil Remediation

Visible Smelter Material Cleanup

Community Relations Plan (August 1994)

Consent Agreement Final Order (Dec. 11, 1992)

Ecological Remediation Plan (Sept. 1997)

Ecological Remediation Record of Decision (Apr. 1998)

Expanded Groundwater Investigation (June 1993)

Final Tributary Inspection

Final Remedial Design Report (May 1997)

First Five Year Review

Focused Feasibility Study (Groundwater)

Groundwater Remediation Proposed Plan

Groundwater Remediation Unit Record of Decision

Proposed Activities July 1992)

Proposed Plan July 1995)

Railroad Spur Remediation Work (Dec. 22, 1998)

Remedial Action Plan Blackwell Schools

Results Phase 1 Groundwater Investigation (Mar. 1992)

Results Expanded Soil Screening (Apr. 1994)

Results Phase 2 Expanded Groundwater Investigation

Results Soil Screening

Results Investigative Action Alternatives

Revised Air Monitoring Procedures

Revised Shallow Soil Investigation and Monitoring Well Installation

Revised Shallow Soil Investigation Work Plan

Revised Supplemental Shallow Soil Investigation Work Plan

Revised Proposed Plan Groundwater Remediation Unit

Record of Decision Soil Remediation Unit

Sampling and Analysis Plan Phase 2 Environmental Assessment 20 Acres

Screening Site Inspection Work Plan

Second Five Year Review

Shallow Soil Investigation and Monitoring Well Installation

Shallow Soil Investigation Report Switching Yard (Oct. 2003)

Shallow Soil Investigation Switching Yard Work Plan (March)

Shallow Soil Investigation Report ROW and 27 Acres (May 2003)

Shallow Soil Remedial Action Work Plan (July 2005)

Site Investigation Work Plan (Oct. 1994)

Soil Consolidation School Park

Soil Remediation Unit Record of Decision

Supplemental Soil Program Quality Assurance Plan

Supplemental Soil Program Remedial Action Plan

Supplemental Soil Program Sampling and Analysis Plan (Rev 1)

Supplemental Shallow Soil Investigation Report (Jan. 2005)

Supplemental Shallow Soil Investigation Work Plan (Mar. 2004)

Storm Water Pollution Prevention Plan for Construction Activities

USEPA & DEQ Memorandum of Understanding

Waste Site Industrial Development

Bartlesville National Zinc

Bartlesville National Zinc Appendices

Blackwell Zinc Groundwater Investigation Unit Final Remedial Design Report (Mar. 13, 1998)

Blackwell Zinc Groundwater Investigation Unit Proposed Phase 1 (Aug, 1991)

Blackwell Zinc Groundwater Investigation Unit Remedial Design Report (Apr 2006)

Data Report Study Action Alternatives

Data Report Study Action Alternatives (2)

Data Report Study Action Alternatives (3)

Final Remedial Design Calculations

Final Remedial Design Calculations (2)

Final Remedial Design Calculations (3)

Final Remedial Design Calculations (4)

2001 Completion Report

SAP Addendum for Large Parcels

Final Tributary Inspection Report

BNSF Blackwell Railway Remedial Activities Completion Report

 

Progress Report Feb. 2013

3rd 5-year Review Report SRU Blackwell Zinc Site new

 