2012 Worksheet for Calculating Closure and
Post-closure Cost Estimates
All site data necessary to calculate estimates of closure and post-closure costs can be gathered by completing table H.1. Data from Table H.1 should be inserted into Tables H.2 and I.1 to complete calculations.
Table H.1 Site Data
Facility
Name:
Permit
Number:
|
Description |
Quantity |
Units |
|
Total Permitted Area |
|
acres |
|
Active Portion |
|
|
|
Composite Lined |
|
acres |
|
Soil Lined |
|
acres |
|
Area of Largest Cell/Phase Requiring Final Cap |
|
|
|
Composite Lined |
|
acres |
|
Soil Lined |
|
acres |
|
Perimeter Fencing |
|
linear feet |
|
Groundwater Monitoring Wells |
|
VLF |
|
Methane Gas Probes |
|
VLF |
|
Terraces |
|
linear feet |
|
Letdown channels |
|
linear feet |
|
Perimeter drainage ditches |
|
linear feet |
|
Average Daily Flow |
|
tons/day |
|
Landfill Disposal Cost |
|
$/ton |
VLF = Vertical linear feet. The sum of the depths of all monitoring wells.
Table
H.2 Closure Cost Estimate
Facility
Name:
Permit
Number:
|
|
Task/Service |
Quantity |
Units |
Multipliera |
Unit
Costb |
Subtotal |
|
1 |
Preliminary
Site Work |
|
|
|
|
|
|
a |
Conduct Site Evaluation |
1 |
Lump sum |
1 |
$3,323.40 |
$3,323.40 |
|
b |
Dispose Final Wastes |
|
|
|
|
|
|
|
Average Daily Flow |
c |
tons/day |
|
|
|
|
|
Disposal Cost |
d |
tons/day |
5 |
e |
|
|
c |
Remove Temporary Building(s) |
1 |
lump sum |
1 |
$3,047.57 |
$3,047.57 |
|
d |
Remove Equipment |
1 |
lump sum |
1 |
$2,487.72 |
$2,487.22 |
|
e |
Repair/Replace Perimeter Fencing |
|
linear feet |
0.25 |
$3.26 |
|
|
f |
Clean Leachate Line(s) |
1 |
lump sum |
1 |
$1,505.27 |
$1,505.27 |
|
2 |
Monitoring
Equipment |
|
|
|
|
|
|
a |
Rework/Replace Monitoring Well(s) |
|
VLF |
0.25 |
$69.89 |
|
|
b |
Plug Abandoned Monitoring Well(s) |
|
VLF |
0.25 |
$27.98 |
|
|
c |
Rework/Replace Methane Probe(s) |
|
VLF |
0.25 |
$60.35 |
|
|
d |
Plug Abandoned Methane Probe(s) |
|
VLF |
0.25 |
$22.05 |
|
|
e |
Rework/Replace Remediation and/or Gas Control Equipment |
1 |
lump sum |
0.05 |
f |
|
|
3 |
Construction |
|
|
|
|
|
|
a |
Complete Site Grading to include on- and off-site borrow areas |
|
acres |
1 |
$1,317.64 |
|
|
b |
Construct Final Cap |
|
|
|
|
|
|
|
Compacted On-site Clay Cap or |
|
cubic yards |
1 |
$4.74 |
|
|
|
Compacted Off-site Clay Cap or |
|
cubic yards |
1 |
$7.68 |
|
|
|
Install Geosynthetic Clay Liner Cap |
|
square feet |
1 |
$0.48 |
|
|
c |
Construct Landfill Gas Venting Layer |
|
|
|
|
|
|
|
Place Sand or |
|
acres |
1 |
$35,232.50 |
|
|
|
Install Net and Geotextile |
|
square feet |
1 |
$0.34 |
|
|
d |
Install Passive Landfill Gas Vents |
|
acres |
1 |
$844.03 |
|
|
e |
Install Flexible Membrane Liner |
|
square feet |
1 |
$0.37 |
|
|
f |
Drainage Layer |
|
|
|
|
|
|
|
Place Sand or |
|
acres |
1 |
$35,232.50 |
|
|
|
Install Net and Geonet |
|
square feet |
1 |
$0.34 |
|
|
g |
Place On-site Topsoil |
|
cubic yards |
1 |
$2.03 |
|
|
|
Place Off-site Topsoil |
|
cubic yards |
1 |
$16.26 |
|
|
h |
Establish vegetative cover, including on- and off-site borrow areas |
|
acres |
1 |
$500.04 |
|
|
4 |
Drainage/erosion
control |
|
|
|
|
|
|
a |
Construct Terraces |
|
linear feet |
1 |
$8.52 |
|
|
b |
Construct Letdown Channels |
|
linear feet |
1 |
$8.00 |
|
|
c |
Clean Perimeter Drainage Ditches |
|
linear feet |
0.50 |
$6.49 |
|
|
5 |
Tasks
Not Identified |
|
|
|
|
|
|
6 |
Subtotal |
|
|
|
|
|
|
7 |
Administrative
Services |
1 |
lump sum |
0.10 |
g |
|
|
8 |
Technical
and Professional Services |
1 |
lump sum |
0.12 |
g |
|
|
9 |
Closure
Contingency |
1 |
lump sum |
0.10 |
g |
|
|
10 |
Total
Final Closure |
|
|
|
|
h |
a Multipliers are determined from the Solid Waste
Financial Assurance Program Report, December 22, 2000.
b Unit costs include a 0.95% inflationary adjustment for
2011.
c New facilities: Insert the value for “W” in OAC
252:515-27-8(a)(2). Existing facilities: Insert reported annual tonnage for the
previous year, divided by 312 operating days per year (52 weeks per year x 6
operating days per week).
d Insert number of tons/day from above.
e Insert landfill disposal cost per ton of
waste ($/ton).
f Input capital cost for gas
control/remediation equipment, if installed at the site.
g Input subtotal from line 6.
h Add rows 6 through 9.
Table
I.1 Post-closure Cost Estimate
Facility
Name:
Permit
Number:
|
|
Task/Service |
Quantity |
Units |
Multipliera |
Unit
Costb |
Subtotal |
|
1 |
Site
maintenance |
|
|
|
|
|
|
a |
Site Inspections |
4 |
per year |
30
8 |
$604.56 |
$72,547.20
$19,345.92 |
|
b |
General Maintenance |
1 |
per year |
30
8 |
$1,812.52 |
$54,375.60
$14,500.16 |
|
c |
Remediation and/or Gas Control Equipment |
1 |
lump sum |
0.3c |
d |
|
|
2 |
Monitoring
equipment |
|
|
|
|
|
|
a |
Rework/Replace Monitoring Well(s) |
|
VLF |
0.25 |
$70.34 |
|
|
b |
Plug Abandoned Monitoring Well(s) |
|
VLF |
0.25 |
$27.98 |
|
|
c |
Final Plugging of Monitoring Wells |
|
VLF |
1 |
$27.98 |
|
|
d |
Rework/Replace Methane Probe(s) |
|
VLF |
0.25 |
$60.35 |
|
|
e |
Plug Abandoned Methane Probe(s) |
|
VLF |
0.25 |
$22.05 |
|
|
f |
Final Plugging of Methane Probes |
|
VLF |
1 |
$22.05 |
|
|
g |
Final Plugging of Piezometer(s) |
|
VLF |
1 |
$22.05 |
|
|
3 |
Sampling
and analysis |
|
|
|
|
|
|
a |
Groundwater Monitoring Wells |
|
wells |
60
16 |
$651.90 e $160.90 |
|
|
b |
Methane Gas Probes |
|
probes |
60 |
$42.30 |
|
|
c |
Surface Water Monitoring Points |
|
points |
60 |
$78.57 |
|
|
d |
Leachate |
|
sample |
60 |
$126.59 |
|
|
4 |
Final
cover maintenance |
|
|
|
|
|
|
a |
Mow and Fertilize Vegetative Cover |
|
acres |
30
8 |
$200.00 |
|
|
b |
Repair Erosion, Settlement, and Subsidence for On-site Soils |
|
acres |
30
8 |
$2.90 |
|
|
|
Repair Erosion, Settlement, and Subsidence for Off-site Soils |
|
acres |
30
8 |
$17.34 |
|
|
c |
Reseed Vegetative Cover |
|
acres |
0.20 |
$500.03 |
|
|
5 |
Leachate
management |
|
|
|
|
|
|
a |
Clean Leachate Line(s) |
1 |
per year |
30 (30 yrs) |
$1,550.27 |
$46,507.98 |
|
b |
Maintain Leachate Collection System and Equipment |
1 |
per year |
30 (30 yrs) |
$2,408.40 |
$72,251.88 |
|
c |
Collect, Treat, Transport, and Dispose of Leachate |
|
gal/yr |
30 |
$0.31 |
|
|
6 |
Tasks
not identified |
|
|
|
|
|
|
7 |
Subtotal |
|
|
|
|
|
|
7 |
Administrative
Services |
1 |
lump sum |
0.06 |
f |
|
|
8 |
Technical
and Professional Services |
1 |
lump sum |
0.07 |
f |
|
|
9 |
Post-closure
Contingency |
1 |
lump sum |
0.10 |
f |
|
|
10 |
Total
Post-closure |
|
|
|
|
g |
a Multipliers are determined from the Solid Waste
Financial Assurance Program Report, December 22, 2000.
b Unit costs include a 0.95% inflationary adjustment for
2011.
c 5% of equipment capital cost, maintenance
performed once per 5 yrs for 30 years.
d Input capital cost for gas
control/remediation equipment, if installed at the site.
e If the
approved groundwater monitoring plan requires monitoring for alternative
constituents, unit costs shall be calculated in accordance with OAC
252:515-27-52(b) or (c).
f Input
subtotal from line 7.
g Add lines 7 through 10.