Interactive NOIs |
New Application Fee for Processing Construction and Industrial NOIsEffective July 1, 2011, DEQ will require payment for both the prorated permit fee and the newly established $100 application fee before issuing an authorization to discharge under DEQ's general storm water permits (OKR10 and OKR05). Please visit the following website to see the changes in OAC 252:606 effective July 1. http://www.deq.state.ok.us/WQDnew/rules/252-606-TXT.pdf Interactive Storm Water Notices of Intent (NOIs)click one of the following links to access the interactive NOI Form 605-002A NOI for Storm Water Discharge Associated With Construction Activity OKR10 Form 605-002B NOI for Storm Water Discharges Associated With Industrial Activity OKR05
Storm Water Program - Construction SitesPermits are required for construction activities that disturb more than one acre, cumulative. This includes the installation or relocation of water or sewer lines that have the potential to disturb more than one acre. Construction activities that are on Indian Country Lands or are at oil and gas exploration and production related industry and pipeline operations that are under the jurisdiction of the Oklahoma Corporation Commission are regulated by the Environmental Protection Agency. Historically, ECLS' involvement with the storm water program was during the investigation of complaints for improper sediment controls or discharges from construction sites. This year, ECLS began processing permit applications and conducting inspections of construction sites that have terminated their permit.
|
Storm Water Program - Industrial SitesNew copy to come
|
|
PermittingA permit to discharge storm water from a construction activity must be obtained prior to the commencement of any soil disturbing activities. To receive a permit the owner/operator of the project must submit a completed Notice of Intent, DEQ Form 605-002A to the ECLS/OKC office. The owner/operator must also develop and implement a Storm Water Pollution Prevention Plan for the site. Permits are non-transferable and may only be terminated at the completion of the project. New owner/operators of existing projects must submit an NOI for the project at least two days before assuming operational control over the site or commencing work on the site. Permits shall be terminated at the completion of the project or when there is a change of owner/operator for the entire project. Termination means that all of the temporary sediment control measures have been removed and that the site has had 70 percent vegetative cover established. The owner/operator terminates a permit by submitting a Notice of Termination, DEQ Form 640-572 to ECLS/OKC.
|
|
Storm Water Pollution Prevention Plan (SWP3)A SWP3 shall be developed for each construction project and will be maintained at the site. The SWP3 shall provide information that pertains to the site description, storm water controls, maintenance, inspections and non-storm water discharges. Construction sites that are located in an Aquatic Resource of Concern as defined in General Permit OKR10 must submit the SWP3 with their NOI. For additional information on the storm water program at construction sites go to the storm water rules or contact Matt Pace at 405/702-6100.
|
|